Project Status

Building Status:

 

Milestone 

Completion Date

Status

1 Preliminary Site Plan Approval

2/25/2009

Complete

2 Submit Final Site Plan to City

5/10/2009

Complete

3 Obtain Wetland Permit

9/18/2009

Complete

4 Obtain City Approval for Final Site

4/30/2009

Complete

5 Submit Final Building Plan to City

6/15/2009

Complete

6 Obtain City Approval for Building

9/30/2009

Complete

7 Evaluate Construction Bids

7/15/2009

Complete

8 First Concrete Poured

12/22/2010

Complete

9 Sannidhi Work in Kanchi India

TBD

In Progress

10 First Floor Walls Completed

April, 2011

Complete

11 Steel Delivered on Site

May, 2011

Complete

12 Steel Structural Work

September, 2011

Complete

13 Concrete Work TBD In Progress

Financial Status:

Total Cost of Temple Construction:  7.5 million

Donations, Loans Commitments to Date:  6 million

Balance of Funds to Raise:  1.5 million

 