Project Status
Building Status:
|
Milestone |
Completion Date |
Status |
1 | Preliminary Site Plan Approval |
2/25/2009 |
Complete |
2 | Submit Final Site Plan to City |
5/10/2009 |
Complete |
3 | Obtain Wetland Permit |
9/18/2009 |
Complete |
4 | Obtain City Approval for Final Site |
4/30/2009 |
Complete |
5 | Submit Final Building Plan to City |
6/15/2009 |
Complete |
6 | Obtain City Approval for Building |
9/30/2009 |
Complete |
7 | Evaluate Construction Bids |
7/15/2009 |
Complete |
8 | First Concrete Poured |
12/22/2010 |
Complete |
9 | Sannidhi Work in Kanchi India |
TBD |
In Progress |
10 | First Floor Walls Completed |
April, 2011 |
Complete |
11 | Steel Delivered on Site |
May, 2011 |
Complete |
12 | Steel Structural Work |
September, 2011 |
Complete |
13 | Concrete Work | TBD | In Progress |
Financial Status:
Total Cost of Temple Construction: 7.5 million
Donations, Loans Commitments to Date: 6 million
Balance of Funds to Raise: 1.5 million