    Building Status:

     

    Milestone 

    Completion Date

    Status

    1 Preliminary Site Plan Approval

    2/25/2009

    Complete

    2 Submit Final Site Plan to City

    5/10/2009

    Complete

    3 Obtain Wetland Permit

    9/18/2009

    Complete

    4 Obtain City Approval for Final Site

    4/30/2009

    Complete

    5 Submit Final Building Plan to City

    6/15/2009

    Complete

    6 Obtain City Approval for Building

    9/30/2009

    Complete

    7 Evaluate Construction Bids

    7/15/2009

    Complete

    8 First Concrete Poured

    12/22/2010

    Complete

    9 Sannidhi Work in Kanchi India

    TBD

    In Progress

    10 First Floor Walls Completed

    April, 2011

    Complete

    11 Steel Delivered on Site

    May, 2011

    Complete

    12 Steel Structural Work

    September, 2011

    Complete

    13 Concrete Work TBD In Progress

    Financial Status:

    Total Cost of Temple Construction:  7.5 million

    Donations, Loans Commitments to Date:  6 million

    Balance of Funds to Raise:  1.5 million

     